Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,000 for direct materials, $8,400 for direct labor, and $6,216 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,000 for direct materials and $5,200 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end?

+4
Answers (1)
  1. 26 June, 21:26
    0
    Overhead = $3,848

    Explanation:

    Giving the following information:

    Sigma Corporation applies overhead costs to jobs based on direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,000 for direct materials, $8,400 for direct labor, and $6,216 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,000 for direct materials and $5,200 for direct labor.

    Estimated manufacturing overhead rate = 6216/8400 = $0.74 per direct labor dollar.

    Job W:

    Overhead = 5,200*0.74 = $3,848
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers