Ask Question
31 March, 04:30

Birk Co. uses a job order cost system. The following debits (credits) appeared in Birk's work-in-process account for the month of April: April Description Amount 1 Balance $ 4,000 30 Direct materials 24,000 30 Direct labor 16,000 30 Factory overhead 12,800 30 To finished goods (48,000) Birk applies overhead to production at a predetermined rate of 80% of direct labor cost. Job No. 5, the only job still in process on April 30, has been charged with direct labor of $2,000. What was the amount of direct materials charged to Job No. 5?

+5
Answers (1)
  1. 31 March, 06:39
    0
    The amount of direct materials charged to Job No. 5 is $5,200.

    Explanation:

    Work in process, April 30 = Balance + Direct material + Direct labor + Factory overhead - Cost of finished goods

    = $4,000 + 24,000 + 16,000 + 12,800 - 48,000

    = $8,800

    Job No 5 = Work in process, April 30 = $8,800

    Job No 5 = Direct material + Direct labor + Factory overhead

    $8,800 = Direct material + $2,000 + $1,600 ($2,000 * 80%)

    Direct material = $8,800 - $2,000 - $1,600

    = $5,200

    Therefore, The amount of direct materials charged to Job No. 5 is $5,200.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Birk Co. uses a job order cost system. The following debits (credits) appeared in Birk's work-in-process account for the month of April: ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers