Type the correct answer in the box. Spell all words correctly.

A movie studio committed to the production of two additional sequels after a successful franchise was launched. However, the story quality of the two sequels was poor and critics gave them low ratings. As a result, attendance figures were very low. What risk did the movie studio suffer from?

___risk negatively impacted the studio's business.

+4
Answers (1)
  1. 13 July, 07:22
    0
    Quality risk

    Explanation:

    Quality risk is a risk that emerges out of failure to meet quality goals for a particular product, service or business practice.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Type the correct answer in the box. Spell all words correctly. A movie studio committed to the production of two additional sequels after a ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.