Which of the following statements is true of costing systems? A. A construction company would likely use a process costing system. B. An accounting firm would likely use a job order costing system. C. A job order costing system would be used by manufacturers of baking utensils. D. A process costing system would be used by manufacturers of customminusmade perfumes.

+3
Answers (1)
  1. 28 October, 21:22
    0
    B. An accounting firm would likely use a job order costing system

    Explanation:

    The job order costing is the cost which is depended upon the various job needs that reflects the differential costing based on the instructions given by the customer.

    On the other hand, the process costing deals with different processes that are held in the company premises.

    As we cant say which costing is used but the job order costing is used by the accounting firm as it gives the various services depending upon the customer needs and for that separate fees is to be charged.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following statements is true of costing systems? A. A construction company would likely use a process costing system. B. An ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.