Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information:

Activity Cost Driver Amount M XY

Production setups Number of setups $ 72,000 12 28

Material handling Number of parts 50,000 54 36

Packaging costs Number of units 355,000 108,000 72,000

$ 477,000

What is the total overhead allocated to Product XY using the current system?

A) $212,400.

B) $190,800.

C) $264,600.

D) $286,200.

+3
Answers (1)
  1. 7 June, 08:17
    0
    Option (B) is correct.

    Explanation:

    Number of units produced in total = M + XY

    = 108,000 + 72,000

    = 180,000

    Total Overhead Cost = $72,000 + $50,000 + $355,000

    = $477,000

    The total overhead allocated to Product XY using the current system:

    = (Total Overhead Cost : number of units produced in total) * Number of Units of Product XY

    = ($477,000 : 180,000) * 72,000

    = $190,800
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.