Ask Question
18 July, 19:52

In December 2016, Shire Computers management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017

+1
Answers (1)
  1. 18 July, 23:28
    0
    redetermined overhead rate = 1.3

    Explanation:

    Giving the following information:

    In December 2016, Shire Computers management establishes the 2017 predetermined overhead rate based on direct labor cost.

    The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in the year 2017.

    predetermined overhead rate = total estimated manufacturing overhead / total amount of allocation base

    predetermined overhead rate=747500 / 575000 = 1.3
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In December 2016, Shire Computers management establishes the 2017 predetermined overhead rate based on direct labor cost. The information ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers