A firm has 56 units of product X on hand. Forecasts of demand are for 20 units per week. An MPS quantity of 100 units is planned to arrive in period 3. Customer orders are 24 for period 1, 18 for period 2, and 15 for period 3. What quantity is available for commitment to new customers prior to the receipt of the MPS quantity in week 3

+4
Answers (1)
  1. 15 March, 09:12
    0
    Answer: 14
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A firm has 56 units of product X on hand. Forecasts of demand are for 20 units per week. An MPS quantity of 100 units is planned to arrive ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.