Four hundred and eighty minutes of production time are available per day. The schedule calls for the production of 80 units per day. Each unit of the product requires 30 minutes of work. What is the theoretical minimum number of workstations?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Four hundred and eighty minutes of production time are available per day. The schedule calls for the production of 80 units per day. Each ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.