Ask Question
19 November, 09:39

Zorn Co. budgeted $600,000 of factory overhead cost for the coming year. Its plantwide allocation base, machine hours, is budgeted at 100,000 hours. Budgeted units to be produced are 200,000 units. Zorn's plantwide factory overhead rate is $6.00 per unit. A) TrueB) False

+3
Answers (1)
  1. 19 November, 12:58
    0
    False

    Explanation:

    Budgeted of factory overhead cost = $600,000

    Budgeted machine hours = 100,000 hours

    Budgeted units to be produced = 200,000 units

    Zorn's plantwide factory overhead rate:

    = Budgeted of factory overhead cost : Budgeted units to be produced

    = $600,000 : 200,000

    = $3 per unit

    Therefore, the answer given in question is false.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Zorn Co. budgeted $600,000 of factory overhead cost for the coming year. Its plantwide allocation base, machine hours, is budgeted at ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers