Activity rates are calculated by a. dividing the budgeted activity cost by the total activity-base usage. b. dividing the total activity-base usage by the budgeted activity cost. c. subtracting the total activity-base usage from the budgeted activity cost. d. multiplying the budgeted activity cost by the total activity-base usage.

+4
Answers (1)
  1. 8 June, 05:29
    0
    Answer: The correct answer is option (A)

    Explanation: Activity rates is calculated by dividing the budgeted activity cost by the total activity-base usage.

    Activity Rate = (Budgeted Activity cost) : (total activity base usage)