If the actual labor rate exceeds the standard labor rate and the actual labor hours exceed the number of hours allowed, the labor rate variance and labor efficiency variance will be:
a)
rate = Favorable efficiency = Favorable
b)
rate = Unfavorable efficiency = Favorable
c)
rate = Favorable efficiency = Unfavorable
d)
rate = Unfavorable efficiency = Unfavorable
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If the actual labor rate exceeds the standard labor rate and the actual labor hours exceed the number of hours allowed, the labor rate ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.