The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs. Group of answer choices True False

+5
Answers (1)
  1. 11 August, 12:18
    0
    True.

    Explanation:

    Indirect cost are cost incurred in the production process that cannot be traced directly back to the product, but contributes to the production process in general. For example the salary of wages is not a cost that is directly included in the product itself, but workers are needed to perform tasks and operate the machines that produce the product.

    Direct cost are traceable directly to the product and include raw material.

    So overhead, facilities and resource opportunity cost are all indirect cost in producing the product.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs. Group of answer choices ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers