Ask Question
28 October, 14:29

Which of the following is the proper Procurement Activity Sequence that is used for every Vendor or Supplier (such as Rebar, Structural Steel and Sheet Metal) on a Design/Build logic network according to acceptable legal practices?

A. Design, Procurement, and Construction

B. Order and Deliver Materials, Place Forms, Place Rebar, Pour Concrete, and Strip Forms

C. Award Vendor Contract, Vendor Prepares Shop Drawings, Contractor Reviews Shops, A/E Reviews Shops, Vendor Fabricates and Delivers

D. Prepare Design Plans, Award Vendor Contract, A/E Approves Design, Order Materials, Fabricate, A/E Approves Shop Drawings, Contractor Approves Shop Drawings, Vendor Delivers Materials

+5
Answers (1)
  1. 28 October, 15:58
    0
    The correct option is option D.

    Explanation:

    The correct order is as

    Prepare Design Plans, Award Vendor Contract, A/E Approves Design, Order Materials, Fabricate, A/E Approves Shop Drawings, Contractor Approves Shop Drawings, Vendor Delivers Materials
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following is the proper Procurement Activity Sequence that is used for every Vendor or Supplier (such as Rebar, Structural ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers