A marketing consultant uses the job costing system and has a pre-determined overhead rate of $15 per direct labor hour. This amount is based on an estimated overhead of $30,000 and an average time of 5.0 hours per job. Job #521 incurred direct material costs of $50 and 6 direct labor hours costing of $75 per hour. The total cost of job #521 is_.

A. $155.

B. $215.

C. $565.

D. $590

+3
Answers (1)
  1. 14 April, 20:53
    0
    D. $590

    Explanation:

    Predetermined overhead rate = $15 per labour hour

    Direct Material cost = $50

    Labor rate = $75 per hour

    Number of Direct labor hour = 6

    Direct labor cost = 6 x 75 = $450

    Overhead applied cost = Predetermined overhead rate x Direct labor hours

    Overhead applied cost = 15 x 6 = $90

    Total cost = $50 + $450 + $90

    Total cost = $590

    So, the correct answer is D. $590
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A marketing consultant uses the job costing system and has a pre-determined overhead rate of $15 per direct labor hour. This amount is ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.