Andalus Furniture Company has two manufacturing plants, one at Aynor and another at Spartanburg. The cost in dollars of producing a kitchen chair at each of the two plants is given here. Aynor: Cost = 80Q1 + 7Q12 + 93 Spartanburg: Cost = 20Q2 + 3Q22 + 147

WhereQ1 = number of Chairs produced at Aynor

Q2 = Number of Chairs produced at SpartanburgAndalus needs to Manufacture a total of 40 Kitchen Chairs to met an order just received. Howmany chairs should be made at Aynor and how many should be made at Spartanburg in order tominimize production costs.

Min + 100) + s. t. Q1 + Q2 = 40Q1, Q2≥0

a. Using Excel Solver What is the optimal solution for this problem

+4
Answers (1)
  1. 31 January, 12:56
    0
    9 in Aynor and 31 in Spartanburg

    Explanation:

    we need to build the following:

    A B C

    units COST

    Aynor 9 = 93 + 80*B2 + POWER (B2; 2) * 7

    Spartanburg 31 = 147 + 20*B2 + POWER (B2; 2) * 3

    =b2 + b3 = c2 + c3

    We stablish that we want to minimize c3

    changing cell b2 and b3

    with the restriction that must be integer solution and b4 should equal 40
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Andalus Furniture Company has two manufacturing plants, one at Aynor and another at Spartanburg. The cost in dollars of producing a kitchen ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.