The following materials standards have been established for a particular product: Standard quantity per unit of output 4.6 grams Standard price $ 15.05 per gram The following data pertain to operations concerning the product for the last month: Actual materials purchased 3,100 grams Actual cost of materials purchased $ 44,020 Actual materials used in production 2,400 grams Actual output 300 units What is the materials quantity variance for the month?

+5
Answers (1)
  1. 10 September, 04:25
    0
    Direct material quantity variance = $15,351 unfavorable

    Explanation:

    Giving the following information:

    Standard quantity per unit of output 4.6 grams

    Standard price $ 15.05 per gram

    Actual materials used in production 2,400 grams

    Actual output 300 units

    To calculate the material quantity variance we need to use the following formula:

    Direct material quantity variance = (standard quantity - actual quantity) * standard price

    Direct material quantity variance = (4.6*300 - 2,400) * 15.05

    Direct material quantity variance = (1,380 - 2,400) * 15.05 = $15,351 unfavorable
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The following materials standards have been established for a particular product: Standard quantity per unit of output 4.6 grams Standard ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.