In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in iterations (sprints) that are normally: a. no more than one calendar year b. a variable length depending on project scope c. a fixed length of two or four weeks d. assigned to one person on the team

+1
Answers (1)
  1. 23 March, 11:28
    0
    The answer is letter C.

    Explanation:

    A fixed length of two or four weeks.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.