Benny Company budgeted 610 pounds of direct materials costing $18.00 per pound to make 8,000 units of product. The company actually used 650 pounds of direct materials costing $30.00 per pound to make the 8,000 units. What is the direct materials quantity variance?

+5
Answers (1)
  1. 26 September, 11:38
    0
    -$720 unfavorable

    Explanation:

    The computation of the material quantity variance is shown below:

    = Standard Price * (Standard Quantity - Actual Quantity)

    = $18 per pound * (610 pounds - 650 pounds)

    = $18 per pound * - 40 pounds

    = - $720 unfavorable

    Simply we take the difference between the standard quantity and the actual quantity and then multiply it by the standard price so that the correct value can come
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Benny Company budgeted 610 pounds of direct materials costing $18.00 per pound to make 8,000 units of product. The company actually used ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers