Which of the following provides essential project data including objective performance status, cost impact of known problems, identification of emerging problems, possible sources of problems, and schedule deviations from the contract plan?

A. Integrated Master Schedule (IMS)

B. Integrated Program Management Report (IPMR)

C. Cost/Benefit AnalysisWork Breakdown Structure (WBS)

D. Mark for follow up

+2
Answers (1)
  1. 8 October, 08:58
    0
    The correct answer is letter "B": Integrated Program Management Report (IPMR).

    Explanation:

    The Integrated Program Management Report (IPMR) is a legally authorized report containing performance details extracted from the internal Earned Value Management System of the contractor. The IPMR provides an extract on the advance of the agreement including potential problems, costs, and change in schedules.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following provides essential project data including objective performance status, cost impact of known problems, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers