10) Before the year began, Murphy Manufacturing estimated that manufacturing overhead for the year would be $175,500 and that 13,000 direct labor hours would be worked. Actual results for the year included the following: actual manufactring overhead cost : 184,000 actual direct labor hours : 14500 the amount of manufacturing overhead allocated for the year based on direct labor hours would have been?

+1
Answers (1)
  1. 20 February, 00:15
    0
    What is given:

    Budgeted overhead = 175,500

    Budgeted labour hours = 13,000

    So Budgeted overhead per hour = 175500/13000 = 13.5

    Actual labor hours = 14,500

    Amount of manufacturing overhead allocated for the year based on direct labour hours = 14,500*13.5 = 195,750
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “10) Before the year began, Murphy Manufacturing estimated that manufacturing overhead for the year would be $175,500 and that 13,000 direct ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers