Ask Question
5 January, 22:25

If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy?

+1
Answers (1)
  1. 6 January, 00:29
    0
    Full funding policy.

    Explanation:

    This would be a violation of Full funding policy.

    Full funding strategy is a federal budgeting requirement implemented by Congress in the 1950s on the Department of Defense (DOD) that mandates all acquisition expenses of a weapons or piece of military equipment to be financed in the year the object is procured. Hence in the above example there is violation of Full funding strategy.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers