If overhead is applied to individual jobs at a rate of 60% of direct labor costs incurred per job, and $40,000 in materials were used and $15,000 of direct labor was required - what was the overhead costs charged to the job?

+4
Answers (1)
  1. 22 July, 07:03
    0
    Overhead charged = $9,000

    Explanation:

    Overhead cost = 60% x $15,000

    =$9,000

    Hence, the overhead costs charged to the job = $9,000.

    Overhead costs refer to those expenses associated with running a business that can't be linked directly to a particular product or service.

    Hence, this is always apportioned to different products and services using a fair basis that represents how the costs have been consumed or utilized.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If overhead is applied to individual jobs at a rate of 60% of direct labor costs incurred per job, and $40,000 in materials were used and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers