7) Krizun Industries makes heavy construction equipment. The standard for a particular crane calls for 20 direct labor-hours at $24 per direct labor-hour. During a recent period 875 cranes were made. The labor efficiency variance was $1,200 Unfavorable. How many actual direct labor-hours were worked

+1
Answers (1)
  1. 5 July, 12:27
    0
    Number of actual hours worked = 17,550 hours

    Explanation:

    Efficiency variance in labour hours = labour efficiency variance/standard labour cost / hour

    The standard labour cost per hour = $24

    = 1,200/24 = 50 hours

    Labour variance (in hours) = Actual labour hours - Standard hours for the actual units

    The standard labour hours allowed for the actual 875 cranes made:

    = 20 * 875 = 17,500 hours

    let the actual hours be " y "

    50 = y - 17500

    y = 50 + 17500

    y = 17,550 hours

    Number of actual hours worked = 17,550 hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “7) Krizun Industries makes heavy construction equipment. The standard for a particular crane calls for 20 direct labor-hours at $24 per ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.