Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters? Selected Answer:a. parametric estimatingAnswers:a. parametric estimatingb. analogous estimatingc. grass roots estimatingd. empirical estimating
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.