Which of the following statements regarding PERT analysis is true? a. Each activity has two estimates of its duration. b. Project variance is the sum of all activity variances. c. Only critical activities contribute to the project variance. d. The most likely time is equivalent to the expected activity time. e. Project standard deviation is the sum of all critical activity standard deviations.
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following statements regarding PERT analysis is true? a. Each activity has two estimates of its duration. b. Project variance ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Home » Business » Which of the following statements regarding PERT analysis is true? a. Each activity has two estimates of its duration. b. Project variance is the sum of all activity variances. c. Only critical activities contribute to the project variance. d.