The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?

+2
Answers (2)
  1. 12 April, 01:33
    0
    Crash the schedule

    Explanation:

    Crashing is the method to utilize when optimizing has not spared enough time on the calendar. It is a method wherein assets are added to the venture for the least cost conceivable.

    Cost and schedule tradeoffs are broke down to decide how to acquire the best measure of pressure for the least steady cost.
  2. 12 April, 02:52
    0
    Fast Track
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.