One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z, 70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units of component C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.