Ask Question
3 May, 22:10

LO 8.4The variable overhead efficiency variance is caused by the difference between which of the following?

actual and budgeted units

actual and standard allocation base

actual and standard overhead rates

actual units and actual overhead rates

+4
Answers (1)
  1. 3 May, 22:41
    0
    actual and standard overhead rates

    Explanation:

    The overhead efficiency variance is calculated by the following formula

    Overhead efficiency variance = (Standard hours used to make the actual production*Standard cost per hour) - (Actual hours used to make the actual production*Standard cost per hour)

    So based on the above discussion, the answer is actual and standard overhead rates.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “LO 8.4The variable overhead efficiency variance is caused by the difference between which of the following? actual and budgeted units ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers