LO 7.2The direct materials budget is prepared using which budget’s information?

cash payments budget

cash receipts budget

production budget

raw materials budget

+5
Answers (1)
  1. 16 June, 16:13
    0
    correct option is production budget

    Explanation:

    solution

    direct materials budget:

    direct materials budget is to find out materials that are purchased to full fill the requirement of production budget by the specified time period

    and It is presented either any format monthly or quarterly in one annual budget

    so here correct option is C. production budget
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “LO 7.2The direct materials budget is prepared using which budget’s information? cash payments budget cash receipts budget production ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.