Describe free float and how you can use it to your advantage in scheduling and managing a project.

+4
Answers (1)
  1. 2 April, 13:55
    0
    Answer and explanation:

    Free float refers to the time an activity can be delayed in a program without affecting the work to be delivered on the due date, either affecting the beginning of any subsequent activity. The free float allows extending activities until the following step starts which allows the organization to verify the current step they are in was properly completed.

    Besides, in scheduling and managing a project, free-floating can be used as a tool to find out if the program has been completed fulfilling the expectations of the program and if the organization is ready and has all the elements necessary to move forward.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Describe free float and how you can use it to your advantage in scheduling and managing a project. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers