Placker Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $155,000, variable manufacturing overhead of $3.40 per machine-hour, and 50,000 machine-hours. Recently, Job A881 was completed with the following characteristics:
Total machine-hours 100
Direct materials $ 645
Direct labor cost $ 2,300
The total job cost for Job A881 is closest to: (Round your intermediate calculations to 2 decimal places.)
a. $1,295
b. $3,595
c. $2,950
d. $2,945
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Placker Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.