Guillen, Inc. began work on a $7,000,000 contract in 2020 to construct an office building. Guillen uses the completed-contract method. At December 31, 2020, the balances in certain accounts were Construction in Process $1,715,000, Accounts Receivable $240,000, and Billings on Construction in Process $1,000,000. Indicate how these accounts would be reported in Guillen's December 31, 2020, balance sheet.

+3
Answers (1)
  1. 1 December, 14:58
    0
    31 Dec balance sheet

    Construction in process $1715000 Asset Non current Asset

    Accounts receivable $240000 Asset Current asset

    Billings on contract in process $1000000 Liability non current liability
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Guillen, Inc. began work on a $7,000,000 contract in 2020 to construct an office building. Guillen uses the completed-contract method. At ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers