Two contractors are comparing the stages of the design phase for a construction project. Contractor A says that the approval of the completed DD documents by the owner occurs during the design development stage. Contractor B says that the schematic design stage is the last stage that occurs. Which one of the following statements is correct? A) Only Contractor A is correctB) Only Contractor A is correctC) Both Contractor A and Contractor B are correctD) Neither Contractor A and Contractor B are correct
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Two contractors are comparing the stages of the design phase for a construction project. Contractor A says that the approval of the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Home » Business » Two contractors are comparing the stages of the design phase for a construction project. Contractor A says that the approval of the completed DD documents by the owner occurs during the design development stage.