When preparing a direct materials budget, the required purchases of raw materials in units equals: Question 9 options: A) raw materials needed to meet the production schedule + desired ending inventory of raw materials - beginning inventory of raw materials. B) raw materials needed to meet the production schedule - desired ending inventory of raw materials + beginning inventory of raw materials. C) raw materials needed to meet the production schedule + desired ending inventory of raw materials + beginning inventory of raw materials. D) raw materials needed to meet the production schedule - desired ending inventory of raw materials - beginning inv

+5
Answers (1)
  1. 14 July, 06:05
    0
    A. Materials to purchase = RM needed for production + RM ending - RM beginning

    Explanation:

    There are already RM in stock which can satisfy partially RM for production need and RM for desired ending stock so for this amt, purchase should be lowered.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “When preparing a direct materials budget, the required purchases of raw materials in units equals: Question 9 options: A) raw materials ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers