Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the estimated direct labor-hours were 22,200 hours and the total estimated manufacturing overhead was $594,960. At the end of the year, actual direct labor-hours for the year were 22,150 hours and the actual manufacturing overhead for the year was $594,960. Overhead at the end of the year was:a. $1,390 underapplied b. $1,340 overapplied c. $1,340 underapplied d. $1,390 overapplied

+3
Answers (1)
  1. 2 January, 13:24
    0
    c. Under applied $ 1,340

    Explanation:

    Computation of predetermined overhead rate

    Estimated manufacturing overhead $ 594,960

    Estimated direct labor hours 22,200 hours

    Predetermined overhead rate per direct labor hour

    $ 594,960 / 22,200 hours $ 26.80 per hour

    Actual Direct Labor hours 22,150 hours

    Applied overhead at predetermined direct labor rate

    $ 26.80 * 22,150 hours $ 593,680

    Actual overhead $ 594,960

    Overhead under applied $ (1,340)