Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, the company planned for activity of 6,200 machine-hours, but the actual level of activity was 6,150 machine-hours. The actual manufacturing overhead for the month was $373,630. 23. The manufacturing overhead in the planning budget for March would be closest to:

A.$373,630

B.$371,650

C.$376,668

D.$374,300

+5
Answers (1)
  1. 9 February, 08:45
    0
    Answer: B
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.