Purves Corporation is using a predetermined overhead rate that was based on estimated total fixed manufacturing overhead of $121,000 and 10,000 direct labor-hours for the period. The company incurred actual total fixed manufacturing overhead of $113,000 and 10,900 total direct labor-hours during the period. The predetermined overhead rate is closest to: a. $10.37 b. $12.10 c. $11.10 d. $11.30

+3
Answers (1)
  1. 19 February, 13:26
    0
    b. $12.10

    Explanation:

    Estimated total fixed manufacturing overhead = $121,000

    Estimated direct labor-hours = 10,000 hours

    Predetermined Overhead rate = Estimated total fixed manufacturing overhead / Estimated direct labor-hours

    Predetermined Overhead rate = $121,000 / 10,000 hours

    Predetermined Overhead rate = $12.10 / labor hour
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Purves Corporation is using a predetermined overhead rate that was based on estimated total fixed manufacturing overhead of $121,000 and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers