A batch of 40 car batteries required $200 of directmaterials and 10 direct labor hours at $15 per hour. Estimated total overhead for the year was $760,000and estimated direct labor hours were 20,000. Whatwould be recorded as the cost of the batch?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A batch of 40 car batteries required $200 of directmaterials and 10 direct labor hours at $15 per hour. Estimated total overhead for the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.