Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. Design modification costs of $155,000 are based on number of design changes. Jackson Company has identified 40,000 batches and has 5,000 design changes in their factory. What is the activity rate for setup?

+2
Answers (1)
  1. 18 May, 16:54
    0
    Answer:52.25
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.