Company Z is just starting to make a brand new product they have never made before. They have completed two units so far. The first unit took 13 hours to complete and the next unit took 11 hours. Based only on this information, what would be the estimate of the learning percentage in this process?

+2
Answers (1)
  1. 8 April, 08:47
    0
    Solution:

    The principle of the learning curve shows that the period to perform a task is multiplied by a set number.

    With this question, we generated the second unit,

    So that we can approximate the percentage of learning from the first unit

    = (Unit 2 time) / (Unit 1 time)

    = 11/13

    = 0.84 ≅ 1

    1 Unit would be the estimate of the learning percentage in this process
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Company Z is just starting to make a brand new product they have never made before. They have completed two units so far. The first unit ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers