Ask Question
5 June, 09:23

Who is responsible for determining how tasks will be done in a weak matrix project management structure?

+5
Answers (1)
  1. 5 June, 11:58
    0
    The correct answer is: The functional manager.

    Explanation:

    A weak matrix project management structure is the type of business organization managed by two executives: the functional manager and the project manager. Both of them work jointly and report to each other accordingly. Out of the two of them, the functional manager is in charge of controlling how work is done within the firm.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Who is responsible for determining how tasks will be done in a weak matrix project management structure? ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers