Ask Question
10 May, 08:49

Athens Machining had one job in Work in Process Inventory at the beginning of the month: Job 1376. Athens has a predetermined overhead rate of $14.00 per direct labor hour. The total direct labor hours were 160 direct labor hours. How much manufacturing overhead (MOH) should the manager allocate to Job 1376?

+5
Answers (1)
  1. 10 May, 11:29
    0
    job N° 1376 manufacturng overhead 2,560

    Explanation:

    For this company, the overhead is calculate based on direct labors.

    It will be calculated by multiplying the cost driver by the overhead rate:

    overhead rate x direct labor hours of job:

    14.00 x 160 = 2,560

    6,400 will be the allocate overhead for job N° 1376

    This will latter be compare with the actual overhead to check for underapplied or overapplied overhead and adjust hte difference.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Athens Machining had one job in Work in Process Inventory at the beginning of the month: Job 1376. Athens has a predetermined overhead rate ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers