You are the project manager for Insomniacs International. Since you don't sleep much, you get a lot of project work done. You're considering recommending a project that costs $575,000; expected inflows are $25,000 per quarter for the first two years and then $75,000 per quarter thereafter. What is the payback period?

+2
Answers (1)
  1. 14 August, 04:59
    0
    The payback period is 13 quarters, which is the same as 39 months.

    Explanation:

    The Payback Period (PBP) represents how long will it take a project to recover the initial investment. It is a tool that can be used for one or multiple projects to compare which one will return the initial investment first.

    To find the answer, we will lay out a table with the information provided in the problem:

    Starting the project we have an initial investment of $575.000 and we will write it down as quarter 0. From then on, for 2 years we will quarterly earnings of $25.000. After 2 years have passed, we will have quarterly earning of $75.000. We will add up the inflows of each quarter until we have a cumulative inflow of $0. This means that, by this quarter, the earnings will be the same as the initial investment.

    Q Inflows Cumulative inflows

    0 - $ 575.000 - $ 575.000

    1 $ 25.000 - $ 550.000

    2 $ 25.000 - $ 525.000

    3 $ 25.000 - $ 500.000

    4 $ 25.000 - $ 475.000

    5 $ 25.000 - $ 450.000

    6 $ 25.000 - $ 425.000

    7 $ 25.000 - $ 400.000

    8 $ 25.000 - $ 375.000

    9 $ 75.000 - $ 300.000

    10 $ 75.000 - $ 225.000

    11 $ 75.000 - $ 150.000

    12 $ 75.000 - $ 75.000

    13 $ 75.000 $ -

    Where Q = Quarter

    We can see that by quarter 13, the initial investment is equal to the cumulative inflows, as it amounts to $0. To find the answer in months, we will proceed to multiply the quarters by 3, as each quarter has 3 months. 13 quarters x 3 months = 39 months.

    In conclusion, the payback period is 39 months.