The City of Oak Park constructed a new storage facility using the city's own public works employees. Construction costs were incurred in the amount of $900,000, plus $25,000 in interest on short-term notes used to finance construction. What amount should be capitalized in the government-wide statements?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The City of Oak Park constructed a new storage facility using the city's own public works employees. Construction costs were incurred in ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.