Sometimes the risks posed by a project are deemed unacceptably large compared to the potential benefits, and the ultimate avoidance strategy is to not perform the project at all. (True/False)

+4
Answers (1)
  1. 31 October, 16:19
    0
    True.

    Explanation:

    In assessment of risk, a firm can employ the use of cost benefit analysis to determine it risk acceptability or avoidance. This can simply be explained as; if the cost of accepting the risk is higher than the benefit/returns from such risk the project is deemed to be rejected.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sometimes the risks posed by a project are deemed unacceptably large compared to the potential benefits, and the ultimate avoidance ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.