Ask Question
23 November, 23:08

The Gardenview Corporation has identified the following overhead costs and activity drivers for next year: Expected Expected Overhead Item Cost Activity Driver Quantity Setup costs $200,000 Number of setups 250 Ordering costs 80,000 Number of orders 1,600 Maintenance 400,000 Machine hours 2,000 Power 40,000 Kilowatt hours 40,000 The following are two of the jobs completed during the year: Job 6A Job 8B Direct materials $3,000 $4,000 Direct labor $2,800 $4,800 Units completed 100 160 Direct labor hours 50 80 Number of setups 1 4 Number of orders 4 5 Machine hours 20 25 Kilowatt hours 30 50

The company's normal activity is 2,000 direct labor hours. If the four activity drivers are used to allocate overhead costs, total overhead allocated to Job 6A would be

a.$5,533.

b.$5,030.

c.$4,830.

d.$5,630.

+1
Answers (1)
  1. 23 November, 23:54
    0
    The correct answer is B.

    Explanation:

    Giving the following information:

    Setup costs $200,000 Number of setups 250

    Ordering costs 80,000 Number of orders 1,600

    Maintenance 400,000 Machine hours 2,000

    Power 40,000 Kilowatt-hours 40,000

    Job 6A

    Units completed 100

    Direct labor hours 50

    Number of setups 1

    Number of orders 4

    Machine hours 20

    Kilowatt-hours 30

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate:

    Setup = ($200,000/250) = 800 per set up

    Ordering costs = (80,000/1,600) = 50 per order

    Maintenance = (400,000/2,000) = 200 per machine hour

    Power = (40,000/40,000) = $1 per kilowatt hour

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Job 6A:

    Set up = 800

    Ordering = 50*4 = 200

    Maintenance = 200*20 = 4000

    Power = 30

    Total = $5030
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The Gardenview Corporation has identified the following overhead costs and activity drivers for next year: Expected Expected Overhead Item ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers