Based on predicted production of 24,000 units, a company anticipates $300,000 of fixed costs and $246,000 of variable costs. If the company actually produces 20,000 units, what are the flexible budget amounts of fixed and variable costs?

+1
Answers (1)
  1. 24 June, 11:57
    0
    Instructions are listed below.

    Explanation:

    Giving the following information:

    Based on the predicted production of 24,000 units, a company anticipates $300,000 of fixed costs and $246,000 of variable costs. The company produces 20,000 units.

    There is no reason or information to determine any change in fixed costs.

    Fixed costs = 300,000

    Variable costs = (246,000/24,000) * 20,000 = $205,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Based on predicted production of 24,000 units, a company anticipates $300,000 of fixed costs and $246,000 of variable costs. If the company ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.