Ask Question
16 June, 14:33

Martinez Aerospace Company uses a job-order costing system. The direct materials for Job #045391 were purchased in July and put into production in August. The job was not completed by the end of August. At the end of August, in what account would the direct material cost assigned to Job #045391 be located?

+5
Answers (1)
  1. 16 June, 17:19
    0
    Answer with Explanation:

    All the direct expenses are formed part of the Work In Progress.

    The entry would be:

    Dr Work In Process Account Job#045391 XX

    Cr Direct Material Inventory Job#045391 XX

    The reason is that the direct expenses are always charged to product under process and once the work in process is converted into finished goods then the sale of the good is recorded with cash to sales and cost of goods sold to Finished godds. These two double entries are as under:

    Recording of sale:

    Dr Trade Receivables XX

    Cr Sales XX

    Recording of finished goods dispatched (inventory sold):

    Dr Cost of goods sold XX

    Cr Finished Goods Job#045391 XX
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Martinez Aerospace Company uses a job-order costing system. The direct materials for Job #045391 were purchased in July and put into ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers