Ask Question
30 August, 10:04

At the beginning of 2019, Florida Road Construction entered into a contract to build a road for the government. Construction will take 4 years. The following information as of 31 December 2009 is available for the contract:

1. Total revenue according to contract $10,000,000

2. Total expected cost $8,000,000

3. Cost incurred during 2009 $1,200,000

Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2009?

A. None.

B. $300,000.

C. $1,500,000.

+5
Answers (1)
  1. 30 August, 12:55
    0
    A. None

    Explanation:

    A is correct because Under the completed contract method, no revenue would be reported until the project is completed.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “At the beginning of 2019, Florida Road Construction entered into a contract to build a road for the government. Construction will take 4 ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers