Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products: Activity Cost Pools Activity Rate Processing customer orders $102.35 per customer order Assembling products $2.65 per assembly hour Setting up batches $54.31 per batch Last year, Product F76D involved 4 customer orders, 495 assembly hours, and 25 batches. How much overhead cost would be assigned to Product F76D using the activity-based costing system?

+2
Answers (1)
  1. 30 October, 06:09
    0
    3,078.9

    Explanation:

    Given that,

    customer orders $102.35 per customer order

    Assembling products $2.65 per assembly hour

    Setting up batches $54.31 per batch

    Total cost:

    = Customer order + Assembly hour + Batch

    = [102.35 * 4] + [2.65 * 495] + [54.31 * 25]

    = 409.4 + 1,311.75 + 1,357.75

    = 3,078.9

    Therefore, the overhead cost that would be assigned to Product F76D using the activity-based costing system is 3,078.9.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.